Project Description

The Eagle County Charter Academy Master Plan consists of five phases. TAB produced color drawings for ECCA to present to the Eagle County School Board.

Phase 1:
ECCA plans to install the roadway and a gravel parking lot in this phase as well as a soccer field on the north part of the property. They will also move in 6 modular buildings to serve as temporary classroom and administrative facilities.

Phase 2:
A gymnasium and assembly area will the first part of the new facilities. The new building is shown in yellow, while the existing modulars are represented in blue.

Phase 3:
The first classrooms to be added will be for 4th through 8th grades. When these new classrooms are completed, two of the modular buildings will be removed from the site.

Phase 4:
The second set of classrooms to be added will be for Kindergarten through 3rd grades. Once these are complete, two more modular units will be removed.

Phase 5:
The final addition will be new administrative facilities, and enlarged parking lot, and an additional parking lot to the west. The final two modular units will then be removed.